Section 10 Establishing connection and verifying the
IEC 61850 communication
10.1 Overview
SEMOD172103-4 v8
The rear optical Ethernet ports are used for:
process bus (IEC/UCA 61850-9-2LE) communication
IEEE C37.118/1344 communication
substation bus (IEC 61850-8-1) communication
10.2 Setting the station communication
SEMOD172108-3 v12
To enable IEC 61850 communication the corresponding ports must be activated. The
rear access points can be used for IEC 61850-8-1 and IEC/UCA 61850-9-2LE
communication. IEC 61850-8-1 redundant communication requires the use of two
Ethernet ports, when it is activated for Ethernet port the next immediate port is selected
as the second Ethernet port and will become hidden.
To enable IEC 61850 station communication:
In this example access points 1, 2 and 3 are used.
1. Activate IEC 61850-8-1 (substation bus) communication.
Navigate to: Main menu/Configuration/Communication/Station
communication/IEC61850–8–1/IEC61850–8–1:1
2. Enable operation for Access Point 1 and 3 in the Ethernet configuration tool
(ECT) in PCM600.
3. Enable redundant communication for Acess point 1 using ECT.
4. Enable IEC/UCA 61850-9-2LE (process bus) communication for Access point 3
by connecting it to a Merging unit in the Merging units tab in ECT.
1MRK 502 073-UUS A Section 10
Establishing connection and verifying the IEC 61850 communication