ABB REG670 - Checking the Power Supply; Energizing the IED; Checking the IED Operation

ABB REG670
324 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Setting list and configuration
RJ-45 Ethernet cable (CAT 5)
Three-phase test kit or other test equipment depending on the complexity of the
configuration and functions to be tested.
PC with PCM600 installed along with the connectivity packages corresponding to
the IEDs to be tested.
Administration rights on the PC, to set up IP addresses
Product documentation (engineering manual, installation manual, commissioning
manual, operation manual, technical manual and communication protocol manual)
4.3 Checking the power supply
M11725-2 v6
Do not insert anything else to the female connector but the
corresponding male connector. Inserting anything else (such as a
measurement probe) may damage the female connector and prevent a
proper electrical contact between the printed circuit board and the
external wiring connected to the screw terminal block.
Check that the auxiliary supply voltage remains within the permissible input voltage
range under all operating conditions. Check that the polarity is correct before
energizing the IED.
4.4 Energizing the IED
4.4.1 Checking the IED operation
M11726-2 v7
Check all connections to external circuitry to ensure correct installation, before
energizing the IED and carrying out the commissioning procedures.
Energize the power supply of the IED to pickup. Keep the DC power supply on until
the Root menu or the selected default screen is shown on the HMI before interrupting
the DC power supply again. The energization could be done in a number of ways, from
energizing a whole cubicle with many IEDs to energizing each single IED one by one.
If HW (i.e. I/O and/or communication boards etc.) have been changed (i.e. removed,
replaced, or added), the user should re-configure the IED by navigating in the local
HMI menu to: Main menu/Configuration/Reconfigure HW modules to activate the
changed hardware modules in order to enable the self-supervision function to detect
possible hardware errors.
Section 4 1MRK 502 073-UUS A
Starting up
46 Generator protection REG670 2.2 ANSI and Injection equipment REX060, REX061, REX062
Commissioning manual