IEC140000143-1-en.vsd
IEC140000143 V1 EN-US
Figure 35: Stop capturing the IEEE C37.118 synchrophasor data
Open the capture file and observe the captured synchrophasor data. In order to get
the Phasor names on top of each column (See figure 36), the capture process
should start before connecting the PMU Connection Tester to the PMU, i.e. first
start the capturing and then click Connect.
Section 11 1MRK 502 073-UUS A
Establishing connection and verifying the IEEE C37.118/1344 communication
120 Generator protection REG670 2.2 ANSI and Injection equipment REX060, REX061, REX062