6 Installation
6.1 Preparing the installation site
1.
Make sure that the installation site complies with the required ambient condi-
tions, see technical data.
2.
Make sure that the surface is flat and clean.
3.
Make sure that the surface can support the weight of the machine and that
the machine is stable.
4.
Make sure that the surface is suitable for fixing the machine down.
5.
Make sure that there is adequate space around the unit. Observe the mini-
mum distances and opening area of the doors.
6.
Make sure that the discharge and air inlet openings are free from obstruction.
Take appropriate measures to ensure that the openings remain clear.