7 Commissioning and operation
7.1 Starting up the unit
7.1.1
Checks before each commissioning
The unit is correctly installed and connected.
All the safety equipment is installed and tested for proper function.
1.
Ensure that only trained, instructed or competent personnel operate the ma-
chine, see Chapter 2.6.2 Personnel selection and qualification, Page 25.
2.
Determine whether maintenance work needs to be performed, see Chap-
ter 9.2 Maintenance table, Page 83.
3.
Perform oil level check and if needed, refill oil, see Chapter 9.4 Maintenance
activities - Lubricating oil system, Page 90.
4.
Perform a visual inspection of all components. If there are any irregularities,
switch off the unit immediately and locate and rectify any errors or get in
touch with the BAUER customer service department, see Chapter 1.1.1 Con-
tact data BAUER KOMPRESSOREN, Page 9.
5.
For first commissioning, observe chapter 'Commissioning the unit for the first
time' in addition.
6.
When commissioning after a long standstill, observe chapter 'Commissioning
the unit after longer downtimes' in addition.
Ä
The unit is ready for operation.