6.4 Having the unit accepted
At the BAUER KOMPRESSOREN factory, components such as the compressor,
storage system and other accompanying assemblies are subjected to a technical
partial acceptance inspection by the TÜV.
Before commissioning the unit, have it inspected at the installation site by a
qualified person or authorised inspection agency, see Chapter 2.7 Safety regu-
lations, Page 27 .