7.1.2 Commissioning the unit for the first time
All compressor units are checked before delivery in the factory so that commis-
sioning can be carried out after proper erection, installation and successful accept-
ance tests. However, the following points must always be observed.
1.
Observe the Chapter 'Check before each commissioning'.
2.
Install the accompanying filter cartridge(s). See Chapter 9.6 Maintenance ac-
tivities filter system, Page 97
3.
Turn the compressor over by hand using the flywheel to check that all compo-
nents are capable of moving freely.
4.
Check all fixing screws for tightness. If needed, re-tighten them with the speci-
fied torque.
5.
Check all screwed pipe fittings for leaks. If needed, re-tighten them with the
specified torque.
6.
Make sure that the rotation direction of the motor is correct, see Chap-
ter 7.1.4 Checking the direction of rotation of the motor, Page 65.