Installing the RTU Open
   
 
 
 
RTU Open v3    CARRIER CORPORATION ©2019  
Installation and Start-up Guide    All rights reserved 
  9 
 
To use an auxiliary control power transformer 
If you use a separate control power transformer, it is essential that the auxiliary transformer and the rooftop 
transformer are in-phase. You 
 verify this prior to connecting the auxiliary transformer to the RTU Open.  
Follow these steps: 
1  Verify the available primary voltage at the rooftop equipment. 
2  Remove power from the rooftop equipment and install the appropriate auxiliary transformer. Follow the 
manufacturer’s installation instructions. 
3  Ground one leg of the auxiliary transformer’s secondary wiring.  
4  Apply power to the rooftop equipment. Measure the potential between the rooftop equipment control power 
and auxiliary transformer's secondary hot (non-grounded) legs. If the voltage measured is less than 5 volts, 
the transformers are in-phase; proceed to step 7. If you measure a voltage greater than 24 Vac, then the 
phases are reversed. 
5  Correct the phase reversal by either of the following methods: 
○  Remove the ground from the secondary at the auxiliary transformer and connect it to the other 
secondary 
○  Reverse the primary wiring at the auxiliary transformer 
6  Repeat step 4 to rewire. 
7  Remove connector assembly from RTU Open's 
 connector. 
8  Connect the auxiliary transformer wires to 
 wires 
(24 Vac) and 
(Gnd). 
9  Apply power to the transformer. 
10  Measure the voltage at the RTU Open’s 
 - 
 and 
 to verify that the voltage is within the operating range of 
21.6–26.4 Vac.  
11  Attach harness to RTU Open's connector 
. See illustration below. 
  The harness connectors are keyed and must be oriented properly for correct installation. 
12  Verify that the 
 LED is on and the 
LED is blinking.