Complete Station Setup
33
Complete the Checklist
Before leaving the installation site, complete
the post-installation checklist.
Customer:
Installer:
Name
Site Address
Contact
Company
Address
Phone
Installer Name
Contact
Earth/ground connection is made to the ground lugs (where applicable).
Installation is ADA compliant with the bottom of the screen no higher than 1220 mm (48 in) and
does not block a ramp or pathway.
Service wiring has been fully inserted into the terminal blocks and all electrical
connections are clean and snug.
The breakers are labeled in the electrical panel.
Electrical enclosures are clean and free of wire strands and metal shavings.
All covers are installed and all fasteners are tightened. The station is fully secured and does
not rock or wiggle.
The two security screws inside the holster plugs on all head assemblies are tightened and
the rubber plugs are in place.
The cable clamps are assembled and have no gaps.
The charging cables operate smoothly through full extension and retraction.
The parking area is clean and free of all packaging and debris.
All pinpointing steps from the Installation Guide have been completed.
Affix Activation Label Here