Handling in Operation
BA_Elmasteam_8_Vers.07.2016 © Elma Schmidbauer GmbH
INFORMATION
We recommend to let the solution react overnight. You
can switch off the device during the reaction time. The
pressure will be dissipated in the pressure vessel
overnight. If the device is switched on after the
reaction time, then the gauge automatically switches
to descaling step 6 The prerequisite hereby is that the
pressure vessel is depressurised!
The
descaling step 6
on the gauge illuminates as
green.
12. Open the pressure vessel screw cap (Figure 6.2.1 Manual
filling).
13. Drain the device completely via the ball valve (Chapter 5.4
Draining).
14. Press the rotary knob to continue with the
descaling step
7
.
The
descaling step 7
on the gauge illuminates as
green.
15. Close the ball valve (Chapter 6.4 Draining).
16. Fill the device with potable water or DI water* (Chapter 6.2
Manual Filling).
17. Press the rotary knob to continue the
descaling step 8
.
The
descaling step 8
on the gauge illuminates as
green.
18. Drain the device completely via the ball valve (Chapter 6.4
Draining).
19. Press the rotary knob to exit the descaling process.
The function
lock
illuminates. The device switches after
descaling automatically to
lock
(Chapter 7.4.4).
INFORMATION
* Preferably operate the device with DI water.
If the water conductivity is < 2μS / cm, then add 1
levelled-off teaspoon of table salt with the initial
commissioning and after descaling. Dissolve the salt in
1 glass of water and fill it via the filling opening into the
device.
ion