2.8 Installation of the probe
Warning
When installing the probe, note the following:
- When the process is in operation, the probe should always be in operation (heated state). A cold
measuring probe during operation can lead to deposits and a shortening of the lifetime of the measuring
probe.
- If maintenance work takes place on the process gas side (e.g. drying heat resistance material, cleaning
with water, removal of old refractory lining, welding, chemical cleaning ...), mechanical and chemical
damage of the measuring probe and the measuring cell can occur.
In such cases, the probe should always be removed from the process.
The flue gas temperature, pressure and all other process conditions must be in accordance with the specification.
Leave enough space for insertion/removal of the probe and protection tube (if supplied) and ensure access to the
measuring probe and/or connecting box. Before cutting a hole in the flue gas duct, make sure that the inside of the
duct has enough space for probe installation and that no soot is blown out nearby or any obstacles are in the way.
For probe lengths exceeding 2000 mm, a support must be mounted inside the duct (every 2m) to prevent the probe
and mounting tube from flexing or bending. ENOTEC recommends installing the probe horizontally for the
fastest possible response time. A vertical (90 °) installation decreases the response time significant.
The ambient temperature at the connection box and the process
temperature may not be exceeded.
Avoid vibrations greater 2g
Mind the IP Code Heavy equipment, ensure proper
lifting and carrying