2. Commissioning
2−56
Festo P.BE−CPX−FB13−EN en 0811c
Faultless commissioning, normal operating status
After faultless commissioning, the LEDs PS (Power System)
and PL (Power Load) light up green.
nformation on the other LEDs for diagnosis and fault
treatment can be found in chapter 3 of this manual and in the
CPX system manual (P.BE−CPX−SYS−...).
LED
Colour Operating status Fault treatment
PS green lights up normal none
PL green lights up normal none
BF
LED is off normal none
Tab.2/20: Normal operating status of the CPX terminal