2.1 GENERAL
TheinstallationofanRB/RBCseriesfuelredsteamboilershouldbecarriedoutbycompetent
personnel in accordance with all relevant safety regulations. It is the responsibility of the installer
to ensure that these regulations are complied with.
SECTION 2 - INSTALLATION
2.2 PRE-INSTALLATION
Prior to delivery of the boiler, consideration should be given to the following:
(Planning regulations may call for more consents than those listed below, always check with your
Local Planning Authority).
A. Local Planning consents where appropriate.
B. Consideration given to access for delivery and positioning of the boiler.
C. Preparation of a suitable base, which must be able to support the total weight of the system
under operating conditions.
The locations of services to the site required for the system, under operating conditions.
D. Electricity supply, check the loading required/available.
E. Drainage system, check the suitability of the drainage system.
F. Local regulations for discharge into existing drains.
G. Suitable access for delivery and off-loading.
H. Safe access to the plant when installation is complete.