After activating and setting the winch, return to the main
display by pressing the button.
Step-for-step
Start the engine and activate the transmitter as described in section 6.4.
Check that the outriggers are extended and that the compact crane is level (see section 6.5).
Check whether the winch plate is between the indicator points. If not, contact your dealer or
Hoeflon International B.V.
Turn the key switch (1) on the electrical cabinet to position 2 'crane' (see figure 30).
Erect the crane by raising the cylinders of boom 1 and the jib in succession, using the
corresponding levers on the transmitter (see section 6.2.1). Then the boom and jib can be
extended. Roll out the winch cable as described below.