9. Install the air baffle.
10. Install the access panel.
11. Install the server into the rack.
12. Connect each power cord to the server.
13. Connect each power cord to the power source.
14. Power up the server.
Removing and replacing the Chassis Intrusion Detection
switch
Procedure
1. Power down the server.
2. Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
3. Do one of the following:
• Extend the server from the rack.
• Remove the server from the rack.
4. Remove the access panel.
5. If GPU is installed on secondary cage, remove the secondary riser cage.
6. Remove the air baffle.
7. Remove the Chassis Intrusion Detection switch.
Removal and replacement procedures 87