Procedure
Step 1 On the home screen of the LCD, choose System Info > Maintenance > Battery
Maint.
Step 2 Tap Start on the right of Capacity Test to start a capacity test.
Figure 7-6 Starting a capacity test
The capacity test automatically stops in any of the following cases:
● The battery discharge voltage reaches the EOD voltage plus 0.01 V.
● The load uctuation exceeds 10%.
● An alarm is generated.
When the battery discharge voltage reaches the EOD voltage plus 0.01 V, the test is
complete. The test data is obtained from the capacity test. Based on monthly capacity test
data, select the test data obtained from a capacity test that has the maximum discharge
capacity as the current-month test data. Save the test data obtained from the latest 36
tests.
----End
7.3 Viewing Test Data
Context
If the UPS does not communicate with SmartLi 3.0, batteries are managed as
lead-acid batteries by default and the battery information is subject to the data
displayed on the SmartLi or NMS.
Procedure
Step 1 On the UPS WebUI, choose Query > Battery Test Records, choose logs that need
to be queried from the Log drop-down list box, and click Query.
SmartLi 3.0
User Manual (Short-Term Backup Power) 7 Maintenance
Issue 10 (2024-01-31) Copyright © Huawei Digital Power Technologies Co., Ltd. 149