Combining Cabinets
● If a BBB box is required when cabinets are combined, install the BBB box by
following the instructions in the
PDU8000-(0630, 1250, 2000) DCV8-BGA001
BBB Box User Manual
.
● If the cabinet is installed against a wall, only the front connecting plates need
to be installed.
Step 1 Install each cabinet in sequence according to the installation method of a single
cabinet.
Step 2 Combine cabinets.
Figure 5-12 Installing connecting kits
----End
5.6 Installing Cables
Ensure that screws are tightened with a torque tool and marked in red and blue
after double-check. Installation personnel mark tightened screws in blue. Quality
inspection personnel conrm that the screws are tightened and then mark them in
red. (The marks should cross the edges of the screws.)
The number and colors of cables in the following gures are for reference only.
SmartLi 3.0
User Manual (Short-Term Backup Power) 5 Installation and Cable Connection
Issue 10 (2024-01-31) Copyright © Huawei Digital Power Technologies Co., Ltd. 70