Figure 5-18 Measuring the cable length
(1) Mark the DT terminal direction (ensure that the installation surface of the DT terminal
is parallel to the copper bar).
(2) Mark the cable cutting position.
2. Remove certain gland sealing plugs. Route the cable through the gland nut
and sealing plugs.
Figure 5-19 Pre-installing a cable gland at the cable
Table 5-6 Mapping between sealing plugs and cable sizes
Gland Model
Sealing Plug to Be Removed Supported Cable
Diameter
(Including the
Insulation Layer,
Unit: mm)
Recommended Cable
Size (Unit: mm
2
)
M63 (18–44) Innermost layer (white stopper
plug)
18–24 150
Innermost layer (white stopper
plug), second-to-last layer (red)
24–30 185
Innermost layer (white stopper
plug), second-to-last layer (red),
and third-to-last layer (orange)
30–37 240
M50 (16–38) Innermost layer (white stopper
plug)
16–20 -
Innermost layer (white stopper
plug), second-to-last layer (red)
20–26 150
Innermost layer (white stopper
plug), second-to-last layer (red),
and third-to-last layer (orange)
26–32 185
SmartLi 3.0
User Manual (Short-Term Backup Power) 5 Installation and Cable Connection
Issue 10 (2024-01-31) Copyright © Huawei Digital Power Technologies Co., Ltd. 75

Table of Contents

Related product manuals