Figure 6-8 Installing ground cables
(1) Ground bar in the equipment room
Step 3 Install power cables.
Cables of the same group, for example, mains input cables, must be routed through the
same cable hole.
● One power source
Figure 6-9 Installing cables
(1) Wiring terminal
(2) Spring washer (3) Bolt
UPS5000-H-(400 kVA-600 kVA)
User Manual (100 kVA Power Module) 6 Installation
Issue 01 (2020-11-30) Copyright © Huawei Technologies Co., Ltd. 61