Step 1521-5
Is there a power supply with a flashing LED?
NO Go to “Step 1521-7”.
YES Go to “Step 1521-6”.
Step 1521-6
Are both I/O drawer power supply LEDs flashing?
NO Replace the power supply with the flashing LED.
This ends the procedure. Go to ″Map 0410: Repair Checkout″ in the
Diagnostics Information for Multiple Bus Systems
YES Check internal drawer cabling from power distribution card to primary I/O
backplane. See “Primary I/O Drawer Internal Cables” on page 483 in Chapter
10.
Replace the following one at a time:
1. primary I/O drawer backplane
2. power distribution board
This ends the procedure. Go to ″Map 0410: Repair Checkout″ in the
Diagnostics Information for Multiple Bus Systems
Step 1521-7
Are all circuit breakers reset at the rack power distribution unit(s)?
NO Reset the circuit breaker.
This ends the procedure. Go to ″Map 0410: Repair Checkout″ in the
Diagnostics Information for Multiple Bus Systems
.
YES Go to “Step 1521-8”.
Step 1521-8
Are all the cables seated firmly and correctly connected between primary I/O
drawer, secondary I/O drawers and CEC drawer?
NO Fix the cable connections.
This ends the procedure. Go to ″Map 0410: Repair Checkout″ in the
Diagnostics Information for Multiple Bus Systems
.
YES Go to “Step 1521-9” on page 93.
92 Service Guide