500 SERIES INSTALLATION MANUAL JULY 2016PAGE 78
Installation Checklist-Outside of Vessel
20.11 Verify Serial #’s on drives for proper ratio and rotation.
20.12 X-Dimension: Conrm proper height. Verify from application drawing.
20.13 Conrm propeller specs for correct diameter and pitch.
20.14 Verify that alignment was done correctly for close couple or remote mount per your install type.
20.15 Conrm proper oil level in sterndrives.
20.16 External Steering: Conrm torque specs on fasteners. Steering rams, tie bars, etc…
20.17 Twin applications: Conrm centerline distance of drives on transom and take measurement from center
to center on propshafts to make sure drives are in-line.
20.18 Inspect all hoses and ttings on trim and steering lines for any leaks at connection points and also
proper routing of hoses.
20.19 Conrm proper orientation of bellows and check for secure connection on drive and gimbal assembly.
Tighten hose clamps.
20.20 Check stern drive for side to side play. The movement should be minimal to none.
20.21 Check for proper continuity on drive from prop shaft to transom using a volt meter.
20.22 Verify correct adjustment of electrical trim senders.
20.23 Inspect bottom of hull for any protrusions impeding clean water ow to propellers. Ex. Transducers,
water pickups, anodes, etc…(See drawing in Installation Guidelines section)
Prepare vessel for sea trail, ll out Application Trial Data Forms on following pages. Send in Konrad Warranty
forms and trial forms to Konrad Marine.