9.2.2 Maintenance Table: Daily Maintenance
At Beginning
of Day
Instrument/Component
Maintenance Task
DiTi cones (LiHa)
Clean
Check for deposits
Tighten
Adjustment check
Air displacement
pipetting arm (Air LiHa)
Clean and inspect DiTi cones
RoMa
Visually check grippers for deformities and damage
During Day
Instrument/Component
Maintenance Task
DiTi waste bag
Check and change when it is full
At End of Day
Instrument/Component
Maintenance Task
Air displacement
pipetting arm (Air LiHa)
Clean and inspect DiTi cones
Carriers and racks
Clean using a detergent or antiseptic solution
Worktable
Clean
Safety panel
Clean
DiTi waste bag
Change
DiTi waste slide and waste station unit
Clean
Lower DiTi eject option
Clean rocker
RoMa standard
Clean gripper fingers using alcohol or acetone
9.2.3 Maintenance Table: Weekly Maintenance
Daily
Maintenance
Daily maintenance
Instrument/Component
Maintenance Task
Reference
Air displacement
pipetting arm (Air LiHa)
Perform the following tests:
Instrument Warm-up
See PyroTec™ PRO Software