5-68 Maintenance and inspection interval
5Maintenance and Inspection
5 Maintenance and Inspection
The maintenance and inspection procedures to be carried out to use the robot for a long time without trouble are
described in this chapter. The types and replacement methods of consumable parts are also explained.
5.1 Maintenance and inspection interval
Maintenance and inspection are divided into the inspections carried out daily, and the periodic inspections carry
out at set intervals. Always carry these out to prevent unforeseen trouble, to maintain the product for a long time,
and to secure safety.
(1) Inspection schedule
Fig. 5-1 Inspection schedule
0Hr
Daily inspection
Monthly inspection
Monthly inspection
Hr Monthly inspection
Monthly inspection
Monthly inspection
Hr Monthly inspection
Monthly inspection
Monthly inspection
Hr Monthly inspection
Monthly inspection
Monthly inspection
Hr Monthly inspection Yearly inspection
Operating time
<Guideline for inspection period>
For one shift
8 Hr/day x 20 days/month x 12 months = approx. 1800 Hr
10 Hr/day x 20 days/month x 12 months = approx. 2400 Hr
For two shifts
15 Hr/day x 20 days/month x 12 months = approx. 3600 Hr
[Caution] According to the schedule on the above, when using the double shift, you should
make the inspections at half the regular intervals.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Mitsubishi CR751-D and is the answer not in the manual?

Mitsubishi CR751-D Specifications

General IconGeneral
BrandMitsubishi
ModelCR751-D
CategoryController
LanguageEnglish

Related product manuals