5. Installation and Connection
5-4
(2) Connecting [SENS] Cable to transformer.
Connect [SENS] Cable from Welding Transformer I/O Signal Connector
(See 4.(2)④) in the rear panel of IPB-5000A to Welding Transformer.
(3) Connecting Start Cable
Connect Start Cable from Terminal Strip for External Input/Output Signal
(See 4.(2)①) in the rear panel of IPB-5000A to Terminal Strip for Start Switch
in Welding Head.
(4) Connecting Voltage Detecting Cable
Connect the Voltage Detecting Cable in the case of using Constant Voltage
Control, Constant Current/Constant Voltage Combination Control and
Constant Power Control.
(5) Connecting a power supply
Connect Input Cable from Breaker for Welding Power Input (See 4.(2)②) in
the rear panel of IPB-5000A to Earth Leakage Breaker.
Connect the earth cable to PE Terminal.
(6) Connecting a necessary External I/O Signal Cable to Terminal Strip for
External Input/Output Signal (See 4.(2)①)