Manual# I27028 4-1 Rev. 2 – 11/22/2017
4 - INSTALLATION
4.1 INSPECTION
1. When the unit arrives, check it immediately for signs of shipping damage. If there is
any noticeable damage, report it to the trucking company right away.
2. Check the outside of the unit. Open the damper for the reactivation blower. Try to
turn the blower by hand. It should turn easily. Do the same with the process
blower. The R10 and R15 process blowers are located within a fan plenum.
3. Remove the access cover on the front of the unit. Check the following items:
• Check to be sure the HoneyCombe
®
wheel is in position. The wheel should be
evenly supported on four rollers.
• Check the seals around both faces of the HoneyCombe
®
wheel for any obvious
signs of damage.
• Check to be sure the drive chain is in place and aligned on its sprocket segments.
• Check to be sure the reactivation air filter is in place.
4. Check the electrical panels and controls:
• Check for any signs of damage.
• Check the tightness of all electrical connections. Carefully check the power wiring
terminals.
• Be sure all control relays are firmly seated in their sockets.
4.2 LIFTING THE UNIT
1. The unit has been provided with fork lift pockets and lifting lugs (cage option only).
2. The weight is shown on each unit. Ensure the crane or fork lift truck has sufficient
capacity for the lift.
3. When using a crane, ensure all four lifting lugs are used (cage option only).
4.3 STACKING THE UNITS (CAGE OPTION ONLY)
1. If the cage option has been purchased, the units may be stacked while on a flat,
level surface.
• R05 may be stacked three units high.
• R10/R15 may be stacked two units high.
2. Ensure that units are stacked in the same orientation, directly on top of each other
to spread the load of the upper unit evenly over the cage frame and maintain the
overall center of gravity of the units.
3. When stacking units, do not slide one unit on top of the other. Lift all four corners
evenly and place the upper unit gently on top of the lower unit.
4.4 POSITIONING THE UNIT
1. Place the unit on a flat, level surface. The General Arrangement drawing is included
with this manual and specifies the required space around the machine.
Consideration should be given to clearances for the following: