Loading...
Data Center
Room Checklist
Items
Yes No N/A Comment
Will the new
hardware
location require
any non-standard
cable lengths?
Is the floor to
ceiling height a
minimum of 2914
mm (114.72
inches)?
Is the depth of
the raised floor a
minimum of 46
cm (18 inches)?
Related Topics:
Space Requirements (page 1-28)
Flooring Requirements (page 1-34)
Stabilize Oracle Exadata Rack with Leveling Feet (page 4-7)
A.3 Data Center Environment Checklist
Use this checklist to ensure that the data center environment requirements have been
addressed.
Data Center
Environment
Considerations
Yes No N/A Comment
Does the
computer room
air conditioning
meet
temperature and
humidity
requirements?
Does the
installation floor
layout satisfy the
ventilation
requirements?
Appendix A
Data Center Environment Checklist
A-5

Table of Contents