Procedure 1: Preparations
No.
Action
Remark
1
Remove any film still in the machine by using
the transport button on the control panel.
See paragraph 5.3.
Save the remains of film for
point 13.
2
Remove the film rolls from the machine. When
heavy rolls are involved (>20 kg) two persons
should do the lifting or lifting gear should be
used.
-
3
Switch off the machine by stopping the
machine and switch the main switch to zero
-
4
Check the machines internally for remains of
product and film; remove manually if
necessary. Remove protective covers and side
plates if so required.
WARNING:
format parts remain hot up
to 1 hour after being shut
down!
5
Check the seals between upper and lower dies
for defects. Remove the covers if necessary.
Inspect visually. If a defect is
found, call the Technical
Department in.
6
Set the main switch on the control cabinet to 1.
7
Replace all protective covers and side plates
on the machine.
See paragraph 4.2.1. for the
locations of the covers.
8
Set the machine to washing setting.
See paragraph 6.1.2
Note: the machines close
automatically
9
Ensure that the control cabinet door is securely
shut.
Visual check.
1.
1.
2.
3.
4.
4.
5.
6.
7.
Transport chain
Chain clips
Tools required:
- scissors/knife
- lifting gear for film rolls
- waste bin
- adhesive tape
- protection film

Table of Contents