Roche Diagnostics
Operatorโs Manual ยท Version 3.1 A-23
Cedex Bio System 2 Introduction to the instrument
Daily operation
7
Performing calibrations
Performing individual
calibrations
1. Start the wizard. Workplace > Calibrations >
2. Select the test. n/a
3. Prepare and place the calibrators. n/a
4. Start the calibration.
5. Validate the calibration results. Workplace > Calibrations >
6. Remove the calibrators.
Performing
all due calibrations
1. Start the wizard. Workplace > Calibrations >
2. Select all tests with due calibrations.
or
Select all tests with calibration due
within the forecast period.
n/a
3. Prepare and place the calibrators. n/a
4. Start the calibration.
5. Validate the calibration results. Workplace > Calibrations >
6. Remove the calibrators.
8
Performing controls
Performing
Default QC
1. Start the wizard. Overview > Order >
2. Select a control and place the tube.
Repeat until there are no controls left
on the screen.
n/a
3. Start the QC measurement.
4. Validate the QC results. Workplace > QC Status >
5. Remove the controls. n/a
Performing an individual
QC measurement
1. Start the wizard. Workplace > QC Status >
2. Select a test. n/a
3. Select a control and place the tube.
Repeat until there are no controls left
on the screen.
n/a
4. Start the QC measurement.
5. Validate the QC results. Workplace > QC Status >
6. Remove the control.
Performing all
due QC measurements
1. Start the wizard. Overview > Order >
>
2. Select a control and place the tube.
Repeat until there are no controls left
on the screen.
n/a
3. Start the QC measurement.
4. Validate the QC results. Workplace > QC Status >
5. Remove the controls.
Task Steps Navigation
With wizard As individual steps
Table A-1 Overview of the daily operation tasks (Continued)