BATTERY CHARGING UNIT
When charging the battery take note of the following:
Step
Procedure
1
Connect battery charger to the charging connector (pos. 1).
Figure 2.1: Pos. 1: Charging connector
Step
Procedure
2 Connect the battery charging unit on 110-230V, 50 - 60Hz power supply.
During the charging procedure, the charge indicating lamp will light up red.
3
At completion of the charging process, the control lamp will change to
green, but the charging current will remain, thus warranting a fully charged
battery.
4 The charging time amounts to approx. 12 hours.
NOTE
The battery charger may be connected to the battery for a longer period, as the
battery takes just the current required to be fully charged.
NOTE
A non-extinguishing red control lamp, even after 24 hours of charging, indicates
that the charging capacity of the battery is diminishing.
NOTE
A red/green blinking of the charging control lamp indicates transition from main
charging to additional charging and does not signal a faulty battery charger.