Commissioning procedure
110-0084.9 / 15 NXAIR / ≤ 40 kA 207
Please visit below website to register to the SIPROTEC and SICAM security update report to receive latest
news.
• www.siemens.com/gridsecurity
Before commissioning please ensure that the firmware of protection relays is up-to-date.
For latest firmware version for Siemens devices please visit below internet site.
• http://w3.siemens.com/smartgrid/global/en/products-systems-
solutions/downloads/Pages/Overview.aspx
For protection relays of other manufacturers please get in touch with the Original Equipment Manufacturer.
14.3 Drying dampness
If the panels become damp by condensation or high humidity, e.g. prevailing during erection, they must be
dried. Use several electrical heaters of 1000 to 2000 W each. Alternatively, the anti-condensation heater must
be switched on if such is part of the switchgear.
The warm air has to flow through all compartments of the switchgear until the panels are completely dry. Take
the withdrawable part / switching-device truck out of the panel to support the air flow.
14.4 Instructing the operating personnel
Make sure that the operating personnel are familiar with all operational details when the
commissioning procedure takes place.
14.5 Checking the accessories
Provide the following accessories to have them ready to hand:
• Operating instructions
• Racking crank for moving the withdrawable part / switching-device truck
• Operating levers for the earthing switches
• Slip-on lever for the shutters (optional)
• Hand crank for the spring energy store
• Racking tool for the removable voltage transformers (optional)
• Double-bit keys
• Circuit diagrams
• Warning signs
• Voltage tester or voltage detecting system
14.6 Checking the interlocks mechanically