Assembling the panels
110-0084.9 / 15 NXAIR / ≤ 40 kA 49
7.4 Aligning the panels
The first transport unit is on the place of installation and the next unit is placed at a distance of approx. 300 mm.
Panel frame
A distorted panel frame will impair the function of the switchgear.
Lay thin shims with 0.5 mm to 1.0 mm thickness under the panel frame, if
required.
Consider the results of the measuring sheet for the foundation.
The first transport unit should be the left end panel.
Observe the minimum distance to the side and the rear wall of the switchgear room in accordance
with the switchgear arrangement.
As for the exact dimension and minimum distance of the panels, refer to the relevant dimension
drawing and arrangement diagram.
Align the panel horizontally.
Align the panel in vertical position.
The first panel may have a level difference of 1mm/m as a maximum.
Lay thin shims with 0.5 mm to 1.0 mm thickness under the panel frame, if required.
Place the next panel at a distance of approximately 300 mm beside the first panel.
The first panel is aligned.