Preparing installation
110-0084.9 / 15 NXAIR / 40 kA 23
Version with bolted floor fixing
Fig. 13: Bolted floor fixing
(1)
Upper edge of finished floor
(7)
Min. 90 mm
(2)
Base frame of panel
(8)
80 mm
(3)
Thread for bolt M12 in the U-profiles of the base frame
(9)
Raw floor
(4)
U-profile U60, DIN 1026
(10)
Expansion dowel with hexagon
head bolt and washer, FAN 12/10
(5)
Floor fixing plate (holder for profiles at a
distance 1200 mm), Fig. 14 "Fig. 14: Side view of the
fixing plate"
(11)
Floor finish
(6)
Min. 55 mm
──
──
Floor fixing plate
NOTICE
Damages due to corrosion
Welded seams are susceptible to corrosion.
After welding, protect the welded seams professionally against corrosion.