Assembling the panels
98 NXAIR / ≤ 40 kA 110-0084.9 / 15
Fig. 122: View from the right: Absorber system
(with lateral deflector plate on the right side
as an example)
Lateral deflector plate mounted on
the right side
Lateral deflector plate mounted on
the left side
Arrowhead pointing to the center
of the switchgear row
Fig. 123: View from the front:
Absorber system installed left of
the center of the switchgear row
Fig. 124: View from the front:
Absorber system installed right of
the center of the switchgear row
Function test for ventilation system (optional version)
Metal grids
The upper metal grids (4) of the ventilation system in the PRC must not be
damaged, i.e. there must be neither cracks nor holes.
Check the metal grids of the ventilation system.
Fig. 125: View onto the ventilation system in the pressure relief duct