Commissioning
5.2 Commissioning workflow
Getting Started, 12/2018, 6SL3097-5AG30-0BP0
65
Creating a project by reading out a device configuration
The following steps are necessary for commissioning a drive by reading out a device
configuration:
1. Create a project with Startdrive (Page 68).
2. Optional: Establish an online connection to the drive. (Page 101)
3. Deriving the hardware device configuration (Page 108).
4. Edit the determined device configuration in Startdrive. (Page 113)
5. Perform the basic parameterization of the drive units. (Page 115)
6. Download the project to the target device (Page 163).
7. Commission the drive via the control panel. (Page 165)
8. Result: The motor turns.