Commissioning
Initial commissioning using vector (chassis) as an example
3-72
E Siemens AG, 2004. All rights reserved
SINAMICS S120 Installation and Start-Up Manual, 12/04 Edition
Table 3-9 Commissioning sequence with STARTER (example), continued
What to do? CommentsHow to do it?
4.1. Active Line
Module
S Enable signals for the Active Line Module
p0840 = 722.4 ON/OFF1
p0844 = 722.5 OFF2
p0852 = 722.6 Enable operation
See function diagram [8920]
4.2. Enable Motor
Module
S Enable signals for the Motor Module (drive_1)
p0840 = 722.0 ON/OFF1
p0844 = 722.1 1st OFF2
p0845 = 1 2nd OFF2
p0848 = 722.2 1st OFF3
p0849 = 1 2nd OFF3
p0852 = 722.3 Enable operation
p0864 = 863.0 Infeed operation
See function diagram [2501]
4.3. Ramp-func-
tion
generator
Ramp-function generator
p1140 = 1 Enable ramp-function generator
p1141 = 1 Start ramp-function generator
p1142 = 1 Enable speed setpoint
See function diagram [3060]
4.4. Setpoint Specify setpoint
p1001 = 40 Fixed speed setpoint 1
p1020 = r0722 Fixed speed setpoint selection
r1024 = p1070 Fixed setpoint effective
A setpoint of 0 or 40 is
defaulted via digital input 7.
This setpoint is then applied
to the main setpoint p1070.
See function diagram [3010]