Mounting and Commissioning 3
This chapter is intended for experienced commissioning staff. The staff must be famil-
iar with the commissioning of protection and control systems, with the management of
power systems and with the relevant safety rules and guidelines. Under certain cir-
cumstances particular power system adaptations of the hardware are necessary.
Some of the primary tests require the protected line or equipment to carry load.
3.1 Mounting and Connections 372
3.2 Checking Connections 396
3.3 Commissioning 401
3.4 Final Preparation of the Device 430