3.2 Checking Connections
399
7SA522 Manual
C53000-G1176-C155-3
Communication
Converter
Optical fibres are usually used for the connections between the devices and commu-
nication converters. The optical fibres are checked in the same manner as the optical
fibre direct connection which means for every protection data interface.
Make sure that under address  &211(&29(5 or  &211(&29(5
the correct connection type is parameterized.
Further Connec-
tions
For further connections a visual control is sufficient for the time being. Electrical and
functional controls are performed during commissioning (see the following main sec-
tion).
3.2.3 Checking System Connections
WARNING!
Warning of dangerous voltages
Non-observance of the following measures can result in death, personal injury or sub-
stantial property damage.
Therefore, only qualified people who are familiar with and adhere to the safety proce-
dures and precautionary measures shall perform the inspection steps.
Caution!
Be careful when operating the device on a battery charger without a battery
Non-observance of the following measure can lead to unusually high voltages and
consequently, the destruction of the device.
Do not operate the device on a battery charger without a connected battery. (For limit
values see also Technical Data, Section 4.1).
Before the device is energized for the first time, the device should be in the final oper-
ating environment for at least 2 hours to equalize the temperature, to minimize humid-
ity and avoid condensation. Connections are checked with the device at its final loca-
tion. The plant must first be switched off and earthed.
Proceed as follows in order to check the system connections:
Protective switches for the power supply and the measured voltages must be
opened.
Check the continuity of all current and voltage transformer connections against the
system and connection diagrams:
Are the current transformers earthed properly?
Are the polarities of the current transformers the same?
Is the phase relationship of the current transformers correct?
Are the voltage transformers earthed properly?
Are the polarities of the voltage transformers correct?
Is the phase relationship of the voltage transformers correct?

Table of Contents

Other manuals for Siemens siprotec 7SA522

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens siprotec 7SA522 and is the answer not in the manual?

Siemens siprotec 7SA522 Specifications

General IconGeneral
BrandSiemens
Modelsiprotec 7SA522
CategoryProtection Device
LanguageEnglish

Related product manuals