Chapter Four – Maintenance Procedures – Base
79
4.6 LIFT UNIT
LIFT MOTOR ISOLATION PLATE REPLACEMENT
(LIFT MOTOR ISOLATION PLATE KIT P/N 3000–200–723)
Required Tools:
#2 Phillips Screwdriver 1/4” Nut Driver 3/8” Open End Wrench
3/8” Socket Wrench 3/16” Punch Hammer
Needle–Nose Pliers 5/16” Nut Driver 7/16” Open End Wrench
3/16” Hex Allen Socket (w/approx. 6” ext.)
A
B
C
D
E
A
C
E
F
Procedure: (This procedure will take approximately 45 minutes)
1. Unplug the power cord from the wall socket.
2. Remove the upper lift cover (see page 67).
3. Remove lower lift cover (see page 67).
4. Remove the front and rear metal access covers (reference the illustration on page 88).
5. Using a 3/16” hex Allen socket with 6” extension, remove the four bolts holding the lift motor to the base
and carefully lower the motor to the floor.