19
5
Mechanical Mounting
Respect all local standards and requirements during mechanical installation.
5.1 Safety Precautions
Only install the product when it is complete and intact.
Before installation, ensure that the product and all internal equipment are intact,
without any damage.
Risk of personal injury or device damage due to incorrect operation!
• Follow the procedure of work of heights when walking on the top of the MV
grid-connected inverter.
• All hoisting and transportation must comply with the relevant codes and regula-
tions of the nation/region where the project is located.
• If any tool is used for unpacking, be careful not to damage the product.
• After receiving the product, check whether the appearance and structural parts
of the product are damaged, whether the transformer leaked oil, and whether
the packing list is consistent with the actual ordered product. If there are prob-
lems with the above inspection items, do not install the product and contact
SUNGROW in time.