This Chapter contains instructions for initial inspection, preparation for use and repackaging for shi
. Connection to PC, setting the communication port and linking Genesys
In order to be operational the power supply must be connected to an appropriate AC source. The AC
hould be within the power supply specification. Do not apply power before reading
1 below, describes the basic setup procedure. Follow the instructions in Table 3
quence given to prepare the power supply for use.
Initial physical inspection of the power su
Installing the power supply,
Connecting the power supply to the AC source
Wire size selection. Local/Remote sensing.
Single or multiple loads.
er supply setting at shipment.
Prior to shipment this power supply was inspected and found free of mechanical or electrical defects.
ing of the power supply, i
nspect for any damage, which may have occurred in transit.
The inspection should confirm that there is no exterior damage to the power supply such as broken
tors and that the front panel and meters face are not scratched or cracked. Keep all
packing material until the inspection has been completed. If damage is detected, file a claim with ca
rier immediately and notify the TDK
Lambda Americas Inc. sales or authorized service facility nearest
series is designed to fit in a standard 19” equipment rack.
3.4.1 To install the Power Supply in a rack:
mount brackets to install the power supply in the rack.
power supplies generate magnetic fields, which
might affect the operation of other instruments. If your equi
ment is susceptible to magnetic fields, do not position it adj
cent to the power supply.