157
General
Operation
Installation
Operation (Service)
Maintenance
i
How to open the storage cabinet and
disassemble the components is described in
Chapter 11.4.
The battery modules should be in a charge
state of 20 to 30% of their capacity.
If necessary, charge or discharge the battery
modules.
The battery modules must be commissioned
again by a qualified electrician certified by
VARTA Storage GmbH within 11 weeks after
the disassembly.
i
Perform commissioning after relocation
according to Chapter 8.