The battery is fully inserted if the battery door fits flush against the UPS.
12. Reattach the battery door with the screws, the replace the front bezels.
13. Follow the appropriate CoHE Procedure to Re-Energize (Turn on) Partially De-energized System.
14. Update the UPS parameters based on those previously installed and customer preference.
15 to 20 kVA MV Replacement without external MBC
1. Download the parameters via ParamSet (if possible) or manually record the parameters from the Setting page.
2. Notify the customer that the load will be de-energized.
Figure 2.18 GXT5-6KL630RT5UXLN
Figure 2.19 GXT5-5000HVRT5UXLN
22 Proprietary and Confidential ©2024 Vertiv Group Corp. 2 Product Description
Vertiv™ Liebert® GXT5 UPS Installer/User Guide