11.3 Verifying the communication
Connect your PC to the nearby switch and ping the connected
IED and the
Substation Master PC, to verify that the communication is working (up to the
transport layer). If it is possible to see all of them, then they can see each other.
The best way to verify the communication up to the application layer is to
use a protocol analyzer, for example an Ethereal that is connected to the
substation bus, and
monitor the communication
Section 11 1MRK 504 088-UEN C
Establishing connection and verifying the IEC 61850 communication