EasyManuals Logo

ABB RET670 Installation And Commissioning Manual

ABB RET670
240 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #169 background imageLoading...
Page #169 background image
1. Connect voltages to the IED according to valid connection diagram and figure
65.
2.
Set Ur (rated voltage) to the U1 inputs and increase U2 voltage until
differential voltage is 1.5 · operating level (UDTrip).
3. Switch on the test set. Measure the time from activation of the START signal
until TRIP signal is activated.
4. Check the measured time by comparing it to the set trip time tTrip.
5. Increase the voltage until START signal resets. Measure the time from reset
of START signal to reset of TRIP signal.
6. Check the measured time by comparing it to the set trip reset time tReset.
13.7.5.4 Final adjustment of compensation for VT ratio differences
Procedure
1. With the protection in test mode, view the differential voltage service values
in each phase on the local HMI under Main menu/Test/Function status/
Voltage protection/VoltageDiff(PTOV,60)/VDCx.
The IED voltage inputs should be connected to the VTs
according to valid connection diagram.
2. Record the differential voltages.
3.
Calculate the compensation factor RFLx for each phase.
For information about calculation of the compensation factor, see the
application manual.
4. Set the compensation factors on the local HMI under Main menu/Settings/
Settings group N/Voltage protection/VoltageDiff(PTOV,60)/VDCx
5. Check that the differential voltages are close to zero.
13.7.5.5 Completing the test
Continue to test another function or end the test by changing the Test mode setting
to Off. Restore connections and settings to their original values, if they were
changed for testing purposes.
13.7.6 Loss of voltage check LOVPTUV
Prepare the IED for verification of settings as outlined in section
"Overview" and
section "Preparing for test" in this chapter.
13.7.6.1
Measuring the operate limit of set values
1MRK 504 088-UEN C Section 13
Verifying settings by secondary injection
163
Installation and commissioning manual

Table of Contents

Other manuals for ABB RET670

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB RET670 and is the answer not in the manual?

ABB RET670 Specifications

General IconGeneral
Rated Frequency50/60 Hz
InputsAnalog and binary inputs
ApplicationProtection of power systems
Communication ProtocolsIEC 61850, DNP3, Modbus
Operating Temperature Range-25°C to +55°C
MountingRack mounted
Number of Binary InputsUp to 48
Number of Binary Outputs32
Protection FunctionsOvercurrent Protection
OutputsBinary outputs
EnclosureIP 54
TypeLine Differential Protection
Number of Analog Inputs24

Related product manuals