EasyManuals Logo

ABB RET670 Installation And Commissioning Manual

ABB RET670
240 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #122 background imageLoading...
Page #122 background image
1. Connect single-phase or three-phase test set to inject the operating voltage.
The injection shall be on the primary side of the stabilizing resistor.
As the operating voltage is adjusted on the stabilizing resistor
and with the setting of the resistor value in the function this is
essential for the measurement of the expected value. Normally
a slightly higher operating value is no problem as the
sensitivity is not influenced much.
2. Connect the trip contact to the test set to stop the test set for measurement of
trip times below.
3.
Increase the voltage and make note of the operate value U>Trip. This is done
with manual test and without trip of the test set.
4. Reduce the voltage slowly and make note of the reset value. The reset value
must be high for this function.
5. Check the operating time by injecting a voltage corresponding to 1.2 ·
U>Trip level. Make note of the measured trip time.
6. If required, verify the trip time at another voltage. Normally 2 · U>Trip is
selected.
7. If used, measure the alarm level operating value. Increase the voltage and
make note of the operate value U>Alarm. This is done with manual test and
without trip of the test set.
8. Measure the operating time on the alarm output by connecting the stop of the
test set to an output from tAlarm. Inject a voltage 1.2 · U>Alarm and measure
the alarm time.
9. Check that trip and alarm outputs operate accordingly to the configuration logic.
10. Finally check that start and alarm information is stored in the event menu and
if a serial connection to the SA is available verify that the correct and only the
required signals are presented on the local HMI and on the SCADA system.
Information on how to use the event menu is found in the operator's
manual.
13.4.3.2 Completing the test
Continue to test another function or end the test by changing the Test mode setting
to Off. Restore connections and settings to their original values, if they were
changed for testing purposes.
Section 13 1MRK 504 088-UEN C
Verifying settings by secondary injection
116
Installation and commissioning manual

Table of Contents

Other manuals for ABB RET670

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB RET670 and is the answer not in the manual?

ABB RET670 Specifications

General IconGeneral
Rated Frequency50/60 Hz
InputsAnalog and binary inputs
ApplicationProtection of power systems
Communication ProtocolsIEC 61850, DNP3, Modbus
Operating Temperature Range-25°C to +55°C
MountingRack mounted
Number of Binary InputsUp to 48
Number of Binary Outputs32
Protection FunctionsOvercurrent Protection
OutputsBinary outputs
EnclosureIP 54
TypeLine Differential Protection
Number of Analog Inputs24

Related product manuals