EasyManuals Logo

ABB RET670 Installation And Commissioning Manual

ABB RET670
240 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #171 background imageLoading...
Page #171 background image
1. Check that the IED settings are appropriate, especially the START value and
the definite time delay.
2.
Supply the IED with three-phase voltages at their rated values.
3. Slowly decrease the frequency of the applied voltage, until the START signal
appears.
4. Note the operate value and compare it with the set value.
5. Increase the frequency until rated operating levels are reached.
6. Check that the START signal resets.
7. Instantaneously decrease the frequency of the applied voltage to a value about
20% lower than the operate value.
8. Measure the time delay of the TRIP signal, and compare it with the set value.
Extended testing
1. The test above can be repeated to check the time to reset.
2. The tests above can be repeated to test the voltage dependent inverse time
characteristic.
Verification of the low voltage magnitude blocking
1. Check that the IED settings are appropriate, especially the StartFrequency,
IntBlockLevel, and the TimeDlyOperate.
2. Supply the IED with three-phase voltages at rated values.
3. Slowly decrease the magnitude of the applied voltage, until the BLKDMAGN
signal appears.
4. Note the voltage magnitude value and compare it with the set value
IntBlockLevel.
5. Slowly decrease the frequency of the applied voltage, to a value below
StartFrequency.
6. Check that the START signal does not appear.
7. Wait for a time corresponding to TimeDlyOperate, and make sure that the
TRIP signal not appears.
13.8.1.2 Completing the test
Continue to test another function or end the test by changing the Test mode setting
to Off. Restore connections and settings to their original values, if they were
changed for testing purposes.
13.8.2 Overfrequency protection SAPTOF
Prepare the IED for verification of settings as outlined in section
"Overview" and
section "Preparing for test" in this chapter.
13.8.2.1 Verifying the settings
1MRK 504 088-UEN C Section 13
Verifying settings by secondary injection
165
Installation and commissioning manual

Table of Contents

Other manuals for ABB RET670

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB RET670 and is the answer not in the manual?

ABB RET670 Specifications

General IconGeneral
Rated Frequency50/60 Hz
InputsAnalog and binary inputs
ApplicationProtection of power systems
Communication ProtocolsIEC 61850, DNP3, Modbus
Operating Temperature Range-25°C to +55°C
MountingRack mounted
Number of Binary InputsUp to 48
Number of Binary Outputs32
Protection FunctionsOvercurrent Protection
OutputsBinary outputs
EnclosureIP 54
TypeLine Differential Protection
Number of Analog Inputs24

Related product manuals