Section 3 Overview
About this chapter
This chapter outlines the installation and commissioning of the IED.
3.1
Commissioning and installation overview
The settings for each function must be calculated before the commissioning task
can start. A configuration, done in the configuration and programming tool, must
also be available if the IED does not have a factory configuration downloaded.
The IED is unpacked and visually checked. It is preferably mounted in a cubicle or
on a wall. The connection to the protection system has to be checked in order to
verify that the installation is successful.
1MRK 504 088-UEN C Section 3
Overview
19
Installation and commissioning manual

Table of Contents

Other manuals for ABB RET670

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB RET670 and is the answer not in the manual?

ABB RET670 Specifications

General IconGeneral
Rated Frequency50/60 Hz
InputsAnalog and binary inputs
ApplicationProtection of power systems
Communication ProtocolsIEC 61850, DNP3, Modbus
Operating Temperature Range-25°C to +55°C
MountingRack mounted
Number of Binary InputsUp to 48
Number of Binary Outputs32
Protection FunctionsOvercurrent Protection
OutputsBinary outputs
EnclosureIP 54
TypeLine Differential Protection
Number of Analog Inputs24

Related product manuals