Benchmark 1500 - 2000 Boilers
CHAPTER 3 – OPERATION
OMM-0097_0E AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913 Page 35 of 182
GF-142 Ph.: 800-526-0288 10/01/2015
CHAPTER 3. OPERATION
3.1 INTRODUCTION
The information in this Chapter provides a guide to the operation of the Benchmark Boiler using
the Control Panel mounted on the front of the unit. It is imperative that the initial startup of this
unit be performed by factory trained personnel. Operation prior to initial startup by factory
trained personnel may void the equipment warranty. In addition, the following WARNINGS and
CAUTIONS must be observed at all times.
WARNING!
• ELECTRICAL VOLTAGES IN THIS SYSTEM INCLUDE 120 AND 24
VOLTS AC. IT MUST BE SERVICED ONLY BY FACTORY CERTIFIED
SERVICE TECHNICIANS.
• DO NOT ATTEMPT TO DRY FIRE THE UNIT. STARTING THE UNIT
WITHOUT A FULL WATER LEVEL CAN SERIOUSLY DAMAGE THE
UNIT AND MAY RESULT IN INJURY TO PERSONNEL OR PROPERTY
DAMAGE. THIS SITUATION WILL VOID ANY WARRANTY.
CAUTION
All of the installation procedures in Chapter 2 must be completed before
attempting to start the unit.
3.2 CONTROL PANEL DESCRIPTION
All Benchmark boilers utilize the C-More Control Panel shown in Figure 3-1. This panel contains
all of the controls, indicators and displays necessary to operate, adjust and troubleshoot the
boiler. These operating controls, indicators and displays are listed and described in Table 3-1.
Additional information on these items is provided in the individual operating procedures and