Benchmark 1500 - 2000 Boilers
CHAPTER 4 INITIAL START-UP
OMM-0097_0E AERCO International, Inc. 100 Oritani Dr. Blauvelt, NY 10913 Page 53 of 182
GF-142 Ph.: 800-526-0288 10/01/2015
CHAPTER 4. INITIAL START-UP
4.1 INITIAL START-UP REQUIREMENTS
The requirements for the initial start-up of the Benchmark boiler consists of the following:
Complete installation (Chapter 2)
Set proper controls and limits (Chapter 3)
Perform combustion calibration (Chapter 4)
Test safety devices (Chapter 6)
All applicable installation procedures in Chapter 2 must be fully completed prior to performing
the initial start-up of the unit. The initial start-up must be successfully completed prior to putting
the unit into service. Starting a unit without the proper piping, venting, or electrical systems can
be dangerous and may void the product warranty. The following start-up instructions should be
followed precisely in order to operate the unit safely and at a high thermal efficiency, with low
flue gas emissions.
Initial unit start-up must be performed ONLY by AERCO factory trained start-up and service
personnel. After performing the start-up procedures in this Chapter, it will be necessary to
perform the Safety Device Testing procedures specified in Chapter 6 to complete all initial unit
start-up requirements.
An AERCO Gas Fired Startup Sheet, included with each Benchmark unit, must be completed
for each unit for warranty validation and a copy must be returned promptly to AERCO via e-mail
at: STARTUP@AERCO.COM.
WARNING!
DO NOT ATTEMPT TO DRY FIRE THE UNIT. Starting the unit
without a full water level can seriously damage the unit and may
result in injury to personnel or property damage. This situation will
void any warranty.
NOTE
All applicable installation procedures in Chapter 2 must be
completed before attempting to start the unit.
4.2 TOOLS AND INSTRUMENTATION FOR COMBUSTION CALIBRATION
To properly perform combustion calibration, the proper instruments and tools must be used and
correctly attached to the unit. The following sections outline the necessary tools and
instrumentation as well as their installation.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Aerco Benchmark 2000 and is the answer not in the manual?

Aerco Benchmark 2000 Specifications

General IconGeneral
BrandAerco
ModelBenchmark 2000
CategoryBoiler
LanguageEnglish

Related product manuals