1 Installing the GC
Installation and First Startup 39
Step 10 Install inlet checkout parts
If using a split/splitless inlet, install the liner and O-ring needed for checkout. See the Operation
manual, and the procedures listed in Maintaining Your GC.
If installing a GC/MS system, refer to the GC/MS installation manuals for the correct inlet
hardware to install, as needed.